Scheduled Power Outage

We need to inform our citizens that on June 18 & June 25 we will have a scheduled power outage from 3am until 7am. This will only affect circuits 5 & 6 which have been highlighted on the map below. During this time the transfer station underground electric will be installed by the County contractors for their new building. We will also have City personnel on site. We want to thank the County contractors for working with us and planning for the outage and installation during our low peak time.